Nearly a year ago, on Nov. 26, 2025, the new County Road 16/17 intersection and its bridge over the diversion channel south of Horace opened to traffic, with paving of the approaches set for the following spring. That gave the south end of town its new crossing. The north end is getting a bigger change, and it's coming in pieces. Over the past few years, 64th Avenue South has been rebuilt one stretch at a time from County Road 17 east toward Interstate 29. The last piece is a set of interstate ramps that Fargo engineers expect to open to traffic in fall 2029.
If you're comparing Horace addresses, this road deserves a place on your list. Every piece of it has a public project number, an approval date or a construction season. You can map a house's distance to 64th Avenue today and know roughly what that road is scheduled to become while you own the house.
Starting at the roundabout on County Road 17
The corridor starts at the roundabout Cass County built at County Road 17 and 64th Avenue South in summer 2023. East of there, the City of Horace's project 2023-4 covers 64th Avenue from County Road 17 to 66th Street. On the City of Horace construction projects page, the city describes that stretch as previously a gravel road. Under the project it becomes a three-lane concrete urban street about 3,500 feet long, with one lane each way, a center turn lane, streetlights and a multi-use path.
The same project includes a short street that matters more than its length suggests. A 610-foot stretch of 62nd Street South connects Fargo's Deer Creek Addition to 66th Street South in Horace. Without it, the city notes, Deer Creek could reach Horace only by going west on Deer Creek Parkway to County Road 17. That link turns two neighborhoods on either side of a city line into a connected street grid.
The city's project files also show what's growing along this road. Deer Creek Estates and its Second Addition sit on County Road 17, on either side of Deer Creek Parkway, and get their south access from 64th Avenue. The city's report for the second and third additions lays out 48 residential lots with a concrete shared-use path, a stormwater pond and streetlights. Farther east, 67th Street went in with Southdale Farms Fourth Addition, and 66th Street was built between 76th Avenue and 64th Avenue, with completion planned for July 2024. Land north of the water and sewer project was being platted as Southdale Farms Sixth Addition. The utility extensions were sized for a proposed Southdale Farms Eighth Addition, a proposed Sunset Valley Addition and a proposed Horace elementary school on land owned by the West Fargo Public School District. The city's list also carries project 2025-2, labeled "64th Ave. S. (Diversion - CR17)," with details still to come.
So north Horace's new additions are filling in along a road built to collector-and-arterial standards. That is a different setting from a quiet interior street a mile south, and buyers can now plan around the difference.
Past Drain 27, the road is still a work in progress
Drain 27 marks the Horace city limit. In Horace's 64th Avenue project report, the road east of the drain is described as continuing inside Fargo as a minimum-maintenance road until it reaches 45th Street South. Farther east, Fargo has already done its part. Fargo's project materials for 64th Avenue from 33rd Street to 38th Street called for a three-lane concrete urban street and a new I-29 overpass with no interstate access, with paving and bridge work scheduled to finish by October 2022.
That puts a finished Horace segment at the west end and a finished overpass at the east end. Between them is a stretch of Fargo farmland that is now being platted.
Covey Ranch Third Addition fills the Fargo side
On Sept. 14, 2026, the Fargo City Commission approved the plat for Covey Ranch Third Addition, which has 158 lots in 8 blocks on 153.41 acres. Its addresses run along 43rd Street South, 45th Street South and 64th Avenue South, from 3785 to 4360 64th Avenue South. The same night, commissioners approved developer agreements with Dabbert Custom Homes, Brookstone Property, Enclave Manager and Bank Forward.
The Sept. 14 commission minutes describe the subdivision as bordering two major arterials, 64th Avenue and 45th Street. In the same discussion, the minutes record Commissioner Michelle Turnberg naming Horace and West Fargo as the neighboring cities Fargo's costs for new subdivisions are measured against.
Covey Ranch Third Addition and Southdale Farms front the same road a couple of miles apart. A buyer shopping new construction near 64th Avenue can line up homes in both, one on each side of Drain 27.
The ramps at I-29, planned for 2028 to 2029
The interchange is what ties these pieces together. On Jan. 20, 2026, Fargo commissioners approved Alternative 1, a partial cloverleaf at the existing 64th Avenue overpass. KFGO reported that the design puts a traffic signal at the west ramp intersection and a roundabout at the east ramp intersection, and that engineers said it costs nearly $3 million less than the other build alternatives. In the same report, engineers said the new interchange would relieve congestion at the 52nd Avenue interchange. That is the interchange south Fargo and Horace traffic heads for now.
The money is committed. KFGO reported $21.25 million in federal funding awarded to the project. If Fargo had declined to move forward, that money would have gone back to the North Dakota Department of Transportation, and it could not be shifted to another Fargo project. Engineers expect construction to begin in spring 2028 and the interchange to open to traffic in fall 2029. The city's project page still lists the 2028 construction season as tentative, so treat both dates as a schedule and not as a promise.
At the January meeting, as KFGO reported, Austin Morris of Enclave Development described what's already drawing traffic to the area: "Fargo Public Schools owns 68 acres out here, you have all sports complex, the largest all sports complex in our state that's driving traffic from all across the state for sporting events. You have Capstone School, you have NDSCS." Those destinations are the Fargo Parks Sports Center, Capstone Classical Academy and the North Dakota State College of Science Career Innovation Center, and they sit along the same road Horace's north side uses.
The east side of the overpass is getting traffic calming
The interchange did not pass without objection. In fall 2025, the Forum reported that neighbors east of the overpass worried more traffic would worsen an already difficult road and driveway access. Commissioners approved the interchange and passed a second motion to look at safety for residents east of the overpass.
The result is a $245,000 package. KVRR reported that commissioners voted 5-0 for 100 boulevard trees, driver feedback signs and an enhanced pedestrian crosswalk, paid for through the infrastructure sales tax. The station also reported that the posted speed limit on that stretch is 30 miles per hour and that traffic monitoring found average speeds around 35. WDAY reported ahead of the October vote that staff proposed adding the work to the 2027 capital program.
Fargo is planning for 64th Avenue to carry enough traffic that its own residents asked for trees and speed signs before the ramps exist. A Horace home that backs onto 64th Avenue can expect the same growth in traffic, and on the Horace side the road is already built as a three-lane arterial.
South Horace got its connection first
The diversion crossing at County Roads 16 and 17 opened with gravel approaches, and the Metro Flood Diversion Authority planned asphalt paving and a pedestrian and bike path for spring 2026. For that paving, the authority closed County Road 17 from north of County Road 16 to 112th Avenue South from May 7 to May 28, 2026, with a detour on County Roads 14, 21 and 16.
Between the two ends of town, 76th Avenue South is getting walking and biking access. The Metro COG transportation improvement program lists a City of Horace shared-use path on the south side of 76th Avenue South, from Brink Drive to County Road 17, for 2027 at a project cost of $519,002.
How the schedule lines up
| When | Where | What |
|---|---|---|
| Oct. 2022, scheduled | 64th Ave S, 33rd to 38th St, Fargo | Three-lane concrete street and I-29 overpass, no ramps |
| Summer 2023 | CR 17 and 64th Ave S | Cass County roundabout |
| Nov. 26, 2025 | CR 16/17, south of Horace | Diversion crossing opens to traffic |
| Jan. 20, 2026 | I-29 and 64th Ave S | Fargo approves partial cloverleaf |
| Sept. 14, 2026 | 64th Ave S and 45th St S | Covey Ranch Third Addition plat approved, 158 lots |
| 2027 | 76th Ave S, Brink Dr to CR 17 | Shared-use path programmed |
| Spring 2028, planned | I-29 and 64th Ave S | Interchange construction begins |
| Fall 2029, planned | I-29 and 64th Ave S | Interchange expected to open to traffic |
The other Horace changes we've written about fit around this road. The town-center projects in why Horace now prices above Fargo sit near Main Avenue and You Betcha Drive. The infrastructure differences between additions are covered in our Horace sewer piece. For a buyer weighing a Southdale Farms home against one closer to the old town, the useful questions are how far the house is from 64th Avenue, whether it fronts or backs onto the road, and whether that matters for a commute that is planned to reach I-29 directly starting in fall 2029. Our Horace neighborhood page shows where each addition sits.
If you own a home near 64th Avenue South and want to know how this road shows up in your price, Up North Realty Group can prepare a home valuation for you. If you're buying, we're glad to go over the corridor schedule with you, one addition at a time, before you write an offer.